At their Nov. 26 All Core Devs Consensus meeting, Ethereum developers scheduled the Glamsterdam upgrade for the Hoodi network for Dec. 15 at 19:12 UTC, corresponding to epoch 143,616. As of Nov. 27, 2026, at 23:42:58 UTC+08:00, client teams were expected to have the necessary releases ready early in the week of Nov. 30.
Contract compatibility and block verification
An earlier test scheduled for Oct. 26 was canceled after ChainSecurity warned that the proposed fee changes could alter how existing contracts behave. At the Nov. 26 meeting, some developers raised concerns about potential breakage and the usability of the GAS opcode. Execution-layer teams nevertheless reached rough consensus to ship EIP-8037 without changes.
On the consensus layer, developers adopted PR 5770, which brings RLP into that layer to verify the block hash of a builder’s payload. They deferred PR 5820.
FOCIL and post-quantum priorities
Developers left open whether FOCIL should remain a headline feature of the later Heze/Hegota upgrade. Some participants favored removing it to free up resources for post-quantum cryptography; others argued that both efforts could proceed in parallel. FOCIL retains its SFI headline status pending a review of the full upgrade scope and its implications for the post-quantum roadmap at the next meeting, expected around Dec. 10.
In a separate discussion, Kevaundray proposed using Keccak-256 as a shared hash function across LeanVM, XMSS and Sphinx. Developers weighed Keccak-256 against more standardized hash functions.